Maintenance and Field Replacement
This section discusses the process for replacing switch components.
You must ensure that at least one of the secondary grounding pads on the chassis's front panel is connected to the data center ground. While working on the switches, select grounded, anti-static wrist straps connected to one of the attach points on the switch for grounding yourself and preventing ESD damage to the switch.
Power Supplies
The switches support AC or DC Power supplies. The switches ship with several populated slots depending on the switch model. Empty slots are covered with a blank. To add a new power supply in one of the available slots, remove the blank covering the slot before inserting a new power supply. The following steps are required for ESD protection when adding or replacing power supplies.
- Ensure that the switch is grounded.
- Connect at least one of the secondary grounding pads on the front to the data center ground as needed.
- Ground yourself using a connected, anti-static wrist strap.
- The anti-static ESD wrist strap must be connected to one of the attach points on the switch.
- Remove the power supply to be replaced (Removing AC Power Supply, Removing DC Power Supply) or the blank for the slot (Removing Fabric Module Blank) where the new power supply will be added.
Removing a Power Supply Blank
Removing an AC Power Supply
Installing an AC Power Supply
Perform the following steps to install an AC power supply.
Removing a DC Power Supply
Make sure to remove the ground connection last when removing power.
Installing a DC Power Supply
Perform the following steps to install a DC power supply.
Fabric and Fan Module (Fabric Module)
The fabric and fan modules are hot-swappable. They are accessible from the rear of the switch (Rear Panel). Consider that the module you insert is compatible with the switch and the module you are replacing. If your switch supports one, perform the following steps to remove and replace a fabric and fan module or a fan-only module.
Removing a Fabric Module Blank
Removing a Fabric Module
Installing a Fabric Module
Perform the following steps to install the module.
Removing the Service Provider 7500n series Fan and Safety Guard
ESD GROUNDING STRAP ADDITION
This product must be grounded. Never defeat the ground conductor or operate the equipment without as a suitably installed ground conductor. Contact the appropriate electrical inspection authority or an electrician if you are uncertain that suitable grounding is available. When installing or replacing this product, the ground connection must always be made first and disconnected last, and the person performing the task(s) must wear a grounded ESD (anti-static) strap.
- For the 7504 and 7508, unscrew the two Phillips screws on the back of the fabric module. Rotate the ejector handle(s) 90 degrees back to hard stops and pull the fabric module straight back to remove. Install the replacement fabric module by opening the ejector handle(s), aligning the module in its slot with the same orientation as the original, and sliding it into the slot in the same orientation as the one removed. When the module is seated, rotate the ejector handle(s) forward and fasten the Phillips screws. Do not over-tighten Phillips screws.
- For the 7512, the failed fan replacement requires the removal of the plastic safety guard and the fabric module. First, enter the global configuration mode in the CLI console by issuing the commands enable, then config, followed by env fan-speed override 100 to increase fan speeds. Wait five minutes for the system to sufficiently cool. Unscrew the six captive screws on the outside perimeter of the plastic safety guard. Set the safety guard aside. The fabric module removal and re-installation procedure is the same as the 7504/7508 instructions. Caution: The 7512R fabric module weighs more than 25 lb. Support the module during handling. Reinstall the plastic safety guard and fasten the six captive screws. Issue the env fan-speed auto command in the CLI console for normal operation.
Touch Point Shield (Optional)
Installing the Touch Point Shield
Supervisor Module
The supervisor modules are hot-swappable. They are accessible from the front of the switch. Consider that the module you insert is compatible with the switch and the module you are replacing. Use the following procedure to remove and replace a supervisor module. For the supervisor module locations for your device, refer to the Front Panel.
Removing a Supervisor Module Blank
Removing a Supervisor Module
Installing a Supervisor Module
Perform the following steps to install the module.
linecards
The linecards are hot-swappable. They are accessible from the front of the switch. Consider that the linecard you are inserting is compatible with the switch and the linecard that you are replacing.
Use the following procedure to remove and replace a linecard. If you add a new linecard, remove the blank from the linecard slot and install the new linecard. For the linecard locations on your switch, refer to the Front Panel.